# Running jobs

Once a job has been successfully created, it can be executed. Running a job will perform each selected migration step in order, as defined by the job configuration within its associated project and plan.

This process allows for precise, staged execution of migration activities across Qlik environments.

## Running a job

Do the following:

1. Select the Project  
   On the Jobs tab, in the Project dropdown, ensure that the correct project is selected.

2. Locate the job  
   In the job list, locate the job you want to run.

3. Click Run  
   Under the Actions column of the job, click the Run button to start the job.

4. Verify Run Status  
   The Run Status of the job should now display as `Running`.

5. Refresh the job list  
   To ensure the Run Status is up to date, click the Refresh button in the job list.

6. Monitor the job log  
   To observe real-time execution progress, access the Job Log. See [Accessing a job log](https://help.qlik.com/en-US/migration/Content/AnalyticsMigrationTool/Managing-Jobs/Job-Logs.htm#accessing-a-job-log) for detailed steps.

## Run status types

The Run Status reflects the job's current state. The following status indicators may appear:

* `Created`   
  The job was created but has not yet been executed.

* `Running`   
  The job is currently executing.

  Information note

  Check the Job Log for real-time output.

* `Cancelled`   
  The job was manually cancelled or stopped due to a tool-level error.

* `Completed`   
  The job completed successfully without any issues.

* `CompletedWithWarnings`   
  The job completed, but warnings occurred during execution. For example, a referenced app was missing on the source system.

  Information note

  Look for `[WRN]` tags in the job log.

* `CompletedWithErrors`   
  The job completed, but encountered one or more critical errors. For example, failure to create a space or export an app.

  Information note

  Look for `[ERR]` tags in red in the job log.

* `Failed`   
  The job did not complete due to configuration or runtime errors.

  Information note

  Check the job log for `[ERR]` tags to identify the cause.

## Related pages

* [Creating jobs](https://help.qlik.com/en-US/migration/Content/AnalyticsMigrationTool/Managing-Jobs/Creating-Jobs.htm)
* [Cancelling jobs](https://help.qlik.com/en-US/migration/Content/AnalyticsMigrationTool/Managing-Jobs/Cancelling-Jobs.htm)
* [Deleting jobs](https://help.qlik.com/en-US/migration/Content/AnalyticsMigrationTool/Managing-Jobs/Deleting-Jobs.htm)
* [Editing jobs](https://help.qlik.com/en-US/migration/Content/AnalyticsMigrationTool/Managing-Jobs/Editing-Jobs.htm)
* [Job logs](https://help.qlik.com/en-US/migration/Content/AnalyticsMigrationTool/Managing-Jobs/Job-Logs.htm)